November 4, 200817 yr From Jane's Funding may delay UK's first JSF purchase By Tim Ripley 4 November 2008 UK procurement officials are considering options to push back the first purchase of Lockheed Martin F-35 Lightning II Joint Strike Fighter (JSF) aircraft, amid growing speculation that funding shortfalls are threatening UK participation in the programme. Jane's has learnt that UK Ministry of Defence (MoD) officials have raised the possibility of not buying three low-rate initial production (LRIP) aircraft over the next two years at a cost of some GBP450 million (USD742 million) and delaying purchases until production-standard aircraft are available in the middle of the next decade. A decision not to acquire LRIP JSFs was recently taken by Italy, Lockheed Martin announced on 10 October. The ministry's highest procurement planning group, the Investment Appraisals Board (IAD), is due to make recommendations on the LRIP JSF purchase at its January meeting. However, some ministry sources suggest a delay might be used as a mechanism to save UK participation in the US-led programme by pushing back the JSF spending 'bow wave' until well into the next decade, easing the ministry's 'funding gap' in the near term. The UK MoD was not able to respond to Jane's ahead of publication.
November 4, 200817 yr Author And ... From Jane's Analysis: Reducing F-35 purchase could save UK up to USD5.8bn By Craig Caffrey 31 October 2008 As the UK Ministry of Defence (MoD) struggles to cope with the budgetary pressures of conflicts in Iraq and Afghanistan and a massive equipment modernisation process, major cuts in one or more programmes appear to Jane's to be inevitable. The global financial crisis and the UK's subsequent response in October (including the multi-billion pound buttressing of the banking system and a commitment to increase public spending to offset recession) has since added to the strain felt by the Treasury. Lingering hopes that extra funding would be made available to supplement the defence budget in the short to medium term appear to have been dashed. Despite already scaling back programmes such as the UK Royal Navy's (RN's) Type 45 destroyer (which has dropped from an initial requirement of 12 ships to six at present) and the UK Royal Air Force's (RAF's) Nimrod MRA.4 maritime patrol aircraft (the originally envisaged 21-aircraft order has since dropped to 12), further cuts are expected to be announced in order to address the deficit in the defence budget. Speculation over which projects are most at risk is continuing. Jane's Defence Forecasts believes that one programme that could see drastic cuts is the Joint Combat Aircraft (JCA) programme through which the RAF and RN intend to acquire the Lockheed Martin F-35 Lightning II multirole fighter. According to the MoD, the UK's current planning assumption is to purchase up to 150 short take-off vertical landing (STOVL) aircraft. Jane's believes this total is likely to be reduced down to around 85-100 aircraft when the production contract is finalised, creating savings of at least USD4.5 billion (GBP2.7 billion) to USD5.8 billion in acquisition costs alone. The potential for cutting the programme stems from the fact that JCA is the only high-profile, high-cost project that the MoD could scale back significantly without detrimentally affecting the capabilities of the UK's armed forces in future. A reduction in the number of F-35s procured to as few as 85 aircraft would allow the RAF to maintain its current fast jet combat aircraft inventory levels while at the same time increasing the capability and flexibility of the force.
Create an account or sign in to comment