LCS hits considerable cost overruns

Featured Replies

From DefenseNews

 

Posted 01/11/07 21:45

LCS hits ‘considerable cost overruns’

By CHRISTOPHER P. CAVAS

 

The Littoral Combat Ship (LCS), advertised by the U.S. Navy as a $220 million bargain, is going to come in at considerably more than that, according to a senior Navy official.

“It appears that we’re having considerable cost overruns on it,” Delores Etter, the Navy’s top acquisition official, told reporters Jan. 11.

“We’ve been doing our cost-performance review on the Lockheed Martin ship,” Etter said, noting that as the first of a class, “you’ve got some surprises you didn’t expect. But we’re trying to understand the exact cost increases and we’re working with Lockheed Martin so you’ve got the right numbers.”

Etter vigorously declined to provide any specific cost figures.

“We don’t have numbers at this point. So one of the things I hope you will help us with is not using numbers right now, because we don’t know the numbers. So that has to mean your numbers aren’t accurate if you’ve got numbers.”

Nevertheless, a Navy official said the cost of the ship was “closer to the mid-threes,” or around $350 million. Other, unofficial, figures approach and break the $400 million barrier.

One problem with providing accurate figures is that it appears cost estimates prepared by different groups are being analyzed by the Navy, although officials could not confirm that is the case.

Chief of Naval Operations Adm. Mike Mullen, and Secretary of the Navy Donald Winter were briefed late Jan. 10 on the LCS cost situation, and Etter noted the Navy has “shared this with Congress.”

“At this point you know everything that we feel we can share at this point on LCS,” she told reporters gathered at the Surface Navy Association symposium in Washington.

Navy officials stressed that the cost figures applied only to the USS Freedom, the first LCS, and not to the class a whole, nor to a competing LCS design being built by General Dynamics.

But the price of GD’s first ship also is rising, although one source claimed the price for their first ship remains well under $300 million, and that “the estimate for the second GD ship will be around $240 million to $250 million.”

Construction of the Freedom began in February 2005 at Marinette Marine in Marinette, Wisc. The ship was launched in September and is expected to be delivered to the Navy this summer. A second Lockheed ship is being built at Bollinger Shipyards in Lockport, La. Lockheed plans to alternate construction of its LCS ships between the two builder yards.

General Dynamics is building its ships at Austal USA in Mobile, Ala. Construction of the first GD ship, the Independence, began in November 2005, with delivery scheduled for 2008. GD plans to build all its ships at the Mobile shipyard.

One reason the cumulative cost growth is so apparent on Lockheed’s ship, Navy and industry officials pointed out, is that progress on the Freedom is further along than on other ships. Freedom is about 73 percent complete, Lockheed said, while the Independence is about 50 percent.

Craig Quigley, spokesman for Lockheed Martin, noted a number of reasons for cost growth on the Freedom.

“Keep in mind that this entire process from concept to ship in the water is happening about 60 percent faster than traditional ship processes,” he said. “This is indeed a warship, not a commercial ship. That defines different requirements.”

Quigley said four principle reasons are behind the cost increases:

• First-of-class issues. The first ship in a new class historically experiences cost increases as shipbuilders learn the best ways to build the ships, Quigley pointed out, adding that numerous representatives from the Bollinger shipyard have been in Marinette “to learn those lessons so we don’t learn them again.”

• Vendor issues. Quigley noted that mistakes by General Electric in manufacturing the ship’s reduction gears — critical elements in a ship’s propulsion system — resulted in schedule changes as the builders struggled to keep construction on track while waiting for new gears. Supply issues also arose in getting the right kind of steel for the ship because it was the same high-priority material used by the Army in up-armoring its High Mobility Multipurpose Wheeled Vehicles (HMMWV or Humvee) being used in Iraq. “Both these issues caused a resequencing of production to maintain schedule. And that increased cost,” he said.

• The impact of new Naval Vessel Rules (NVR), regulations being created by the Navy to standardize and strengthen ship construction requirements. “Shortly after the contract was awarded in 2004 the Navy directed a change to the Naval Vessel Rules,” Quigley said. “The tightened NVRs will make a tougher ship. But there is an impact on cost. It is particularly relevant when you’re adapting a commercial design to a naval warship.” Lockheed’s hull form is based on a large, commercial, Italian-designed yacht.

• The impact of a fast-track acquisition program where ships are being put into production while design work still is being carried out. “The Navy and Lockheed Martin always knew this was going to be an element of moving a ship along this fast,” Quigley said. “You’re not going to get a ship in the water in four years unless you do this. But this was exacerbated when the Navy imposed the use of NVR, which introduced more concurrency, more redesign and reconstruction.”

“We will continue to work very closely with the Navy,” Quigley added, “to understand these cost increases and put the best and most affordable warship we can to sea.”

Navy and General Dynamics officials said it was too early to assess the cumulative impact of cost growth on the Independence.

“It is premature to draw any conclusions about the General Dynamics ship as it is only about 50 percent complete,” said GD spokesman Kendell Pease.

  • Author

From DefenseNews

 

Posted 01/12/07 17:58

Stop-Work Ordered for Third LCS

U.S. Navy Struggles To Rein In Soaring Program Costs

By CHRISTOPHER P. CAVAS

 

Scrambling to regain control of Littoral Combat Ship (LCS) program costs and forestall a congressional firestorm, U.S. Navy leaders have called for a temporary halt on construction on the third LCS while examining why cost growth on the first one has jumped as much as 86 percent.

A recent cost review of the USS Freedom (LCS 1) showed that the estimated price had jumped from a planned $220 million to between $331 million and $410 million, according to a Navy official. That ship is under construction by Lockheed Martin and scheduled to be delivered to the Navy this summer.

The third ship is in fabrication, an early stage of construction.

As a result of the findings, Navy Secretary Donald Winter decided on Jan. 12 to put out a 90-day stop-work order on Lockheed’s second ship until the causes of the cost growth are found and a way ahead is determined.

The Navy, a service official said Jan. 12, needs to “fully understand whether the cost problems are unique to the lead ship or an indicator of increased follow-on ship costs” before building more Lockheed ships.

Service leaders have been aware of cost growth in the LCS program, but until recently were not aware of the extent.

“It appears that we’re having considerable cost overruns on it,” Delores Etter, the Navy’s top acquisition officer, told reporters Jan. 11. “We don’t know the numbers.”

Etter spoke a week after deciding to reassign the program executive officer for ships, Rear Adm. Charles Hamilton, to a position outside the Naval Sea Systems Command (NAVSEA). Sources said the reassignment was not due solely to problems with the Littoral Combat Ship.

The Navy is examining cost estimates prepared by several groups, including the Navy’s LCS program manager, NAVSEA, Lockheed Martin and the Pentagon’s Cost Analysis Improvement Group (CAIG).

Navy officials would not reveal specific cost estimates by each group, although the estimates range from 50 percent to 86 percent above the hoped-for $220 million price tag.

On Jan. 10, Etter briefed Winter and Adm. Mike Mullen, chief of naval operations (CNO), on the situation. She said the Navy has also “shared this with Congress.”

Service leaders met again Jan. 12 to decide how to proceed.

Navy officials stressed that the cost figures applied only to the Freedom, the first LCS, and not to a competing LCS design being built by General Dynamics (GD).

But the price of GD’s first ship also is rising, although one source claimed the price for the first GD ship remains well under $300 million, and that “the estimate for the second GD ship will be around $240 million to $250 million.”

As a result of the cost analysis on the Freedom, a Navy official said, a similar cost review will be performed on the General Dynamics ship.

Centerpiece at Stake

The 55-ship Littoral Combat Ship program is a centerpiece of Mullen’s 313-ship fleet plan.

But Congress has been less than pleased with the cost estimates.

A year ago, the Navy increased the projected per-ship cost to about $300 million. Senate appropriators were dissatisfied enough with the Navy’s explanations to recommend turning down the 2007 request for two ships and rescinding funds for the third of three authorized in 2006 until the service could get a handle on LCS costs. Although those threats died in conference, Congress said its concerns remained and told the Navy to do a better job at cost estimation or risk greater oversight.

The service clearly is worried about cost growth.

“They’ll take a lot of heat from the Hill from this,” said one congressional naval analyst familiar with the program. “There are a lot of people on the appropriations and armed services committees who have not been happy with the relatively modest cost increases that have occurred in the program.

“Now if we’re talking about greater cost increases they’re going to be extraordinarily unhappy, and the Navy should expect much greater oversight into how it’s managing the program, especially as [in a Democrat-controlled Congress] this is seen as very much a Bush and Rumsfeld program.”

Construction of the Freedom began in February 2005 at Marinette Marine in Marinette, Wis. The ship was launched in September and is expected to be delivered to the Navy this summer. A second Lockheed ship — upon which the Jan. 12 stop-work order was aimed — is being built at Bollinger Shipyards in Lockport, La. Lockheed plans to alternate construction of its LCS ships between the two builder yards.

General Dynamics is building its ships at Austal USA in Mobile, Ala. Construction of the first GD ship, the Independence, began in November 2005, with delivery scheduled for 2008. GD plans to build all its ships at the Mobile shipyard.

One reason the cumulative cost growth is so apparent on Lockheed’s ship, Navy and industry officials pointed out, is that progress on the Freedom is further along than on other ships. Freedom is about 73 percent complete, Lockheed said, while the Independence is about 50 percent.

A cost analysis like that done on the Freedom hasn’t yet been performed for the Independence.

“It is premature to draw any conclusions about the General Dynamics ship,” GD spokesman Kendell Pease said Jan. 11.

But that doesn’t mean GD’s ship isn’t affected by cost concerns.

“If we find that the GD ship is experiencing the same type of cost growth,” the congressional naval analyst said, “then Congress is left with a choice — they can either act to dramatically scale-back the program, or cancel it. Or they could take a wait-and-see approach to see if maybe these are lead ship problems and maybe the Navy can bring the cost back down.

“If, however, the GD ship does not have the same type of cost growth,” the Congressional naval analyst added, “there is going to be very intense pressure from Capitol Hill for the Navy to down select to one design rather than the Navy’s current plan to buy a total of 15 before making a decision.”

Another factor in gauging Congressional response to the program’s cost growth, the Congressional naval analyst pointed out, is that the ships are being built at three small shipyards that have not done a lot of Navy work.

“People from the big yards” — the six major shipyards owned by Northrop Grumman and General Dynamics — “have always regarded LCS as a threat,” the analyst said. “This doesn’t help that.”

Fast-Track Pace

The pace of acquisition is key to the Navy’s desire to rapidly get the ships in service to perform close-to-shore combat missions.

Championed by previous CNO Adm. Vern Clark, the LCS is aimed at filling a gap where the Navy’s blue-water warships are less effective or too expensive to be risked.

The program has been on an exceptionally fast track from its inception in 2002, and rather than building larger and more costly ships loaded with weapons and sensors, the Navy has developed a modular plan to shift equipment on and off ships depending on a particular mission.

The service is anxious to begin getting actual sea experience with the ships to flesh out their concepts of operations. Any change in the acquisition plan could ripple through the service’s wish to develop operations and send the ships overseas to areas they’re needed.

A factor in the rapid development of the program is the large number of new-to-the-U.S. Navy components in the ships due to their relatively small size. About 20 percent of the equipment is foreign-supplied or designed, and a number of companies offered their products at near- or below-cost to enter the potentially lucrative U.S. Navy market.

Although Navy officials declined to cite specific factors leading to price hikes on the Freedom, Lockheed spokesman Craig Quigley cited a number of reasons.

• The first ship in a new class historically experiences cost increases as shipbuilders learn the best ways to build the ships. Quigley noted that numerous representatives from the Bollinger shipyard have been in Marinette “to learn those lessons so we don’t learn them again.”

• Vendor issues. Quigley noted that mistakes by General Electric in manufacturing the ship’s reduction gears slowed the schedule. It was also tough to get the right kind of steel, which was also being ordered by the Army to up-armoring vehicles in Iraq.

• The Navy’s new Naval Vessel Rules (NVR), changed in 2004 to to standardize and strengthen ship construction requirements. Quigley said, “The tightened NVRs will make a tougher ship. But there is an impact on cost. It is particularly relevant when you’re adapting a commercial design to a naval warship.” Lockheed’s hull form is based on a large, commercial, Italian-designed yacht.

• A fast-track acquisition program that puts ships into production while design work still is going on. “The Navy and Lockheed Martin always knew this was going to be an element of moving a ship along this fast,” Quigley said.

Create an account or sign in to comment

Account

Navigation

Search

Search

Configure browser push notifications

Chrome (Android)
  1. Tap the lock icon next to the address bar.
  2. Tap Permissions → Notifications.
  3. Adjust your preference.
Chrome (Desktop)
  1. Click the padlock icon in the address bar.
  2. Select Site settings.
  3. Find Notifications and adjust your preference.